Dewatering at the Palm Jumeirah, Dubai

Dubai Palm Jumeirah is a home to many luxurious hotels, apartments and villa’s. Khansaheb Sykes has been approached for dewatering at this prestigious location for the construction of 5 new villas.

The main challenge faced with the dewatering was the site location proximity to the sea, which is hardly a few feet away. Our site investigation and prior knowledge of subsoil and water table level enabled us to recommend and install the most appropriate system. Being well experienced in handling the toughest of the dewatering and groundwater control projects enabled our team to build a well point wall around the entire area where the construction was taking place.

As the site is very near to the sea, the well points have been installed in close proximity to each other so as to keep away pressured water from obstructing the construction schedule. Our well point dewatering pumps WP150/60 were fitted with high capacity vacuum pumps to achieve the maximum drawdown and a number of well points could be installed.

A full proof dewatering solution is being provided to the client who has now begun with the construction of the villas. They were happy with the timely progress of their project without any obstructions.